The planned activities for
the week of 4/1/02 are as follows:
- Continue installing peat in the wetland area along the edge of Paintshop
Pond.
- Continue storm drain installation along the south side of the Distribution
Center building.
- Complete installation of select borrow over the engineered barrier.
- Continue granite work around Paintshop Pond dam.
- Place channel stone subgrade.
- Touch-up grading of the Waban Brook channel and adjacent peat in
the southern wetland.
- Continue subgrade and finish grading across site.
Activities conducted during
the week of 3/25/02 include:
- Placement and compaction of fill
- Continued granite work around Paintshop Pond dam.
- Continued restoration work.
- Continued preparing subgrades across site.
- Installing storm drain system.
- Completed installation of the perimeter and interior drain over the
engineered barrier.
- Placed select borrow soil fill over the engineered barrier geosynthetics.
- Placing peat along the edge of Paintshop Pond wetland area.
- Installing steel grating over the Paintshop Pond dam walkway.