The planned activities for the week of 4/1/02 are as follows:

  1. Continue installing peat in the wetland area along the edge of Paintshop Pond.
  2. Continue storm drain installation along the south side of the Distribution Center building.
  3. Complete installation of select borrow over the engineered barrier.
  4. Continue granite work around Paintshop Pond dam.
  5. Place channel stone subgrade.
  6. Touch-up grading of the Waban Brook channel and adjacent peat in the southern wetland.
  7. Continue subgrade and finish grading across site.

    Activities conducted during the week of 3/25/02 include:
  1. Placement and compaction of fill
  2. Continued granite work around Paintshop Pond dam.
  3. Continued restoration work.
  4. Continued preparing subgrades across site.
  5. Installing storm drain system.
  6. Completed installation of the perimeter and interior drain over the engineered barrier.
  7. Placed select borrow soil fill over the engineered barrier geosynthetics.
  8. Placing peat along the edge of Paintshop Pond wetland area.
  9. Installing steel grating over the Paintshop Pond dam walkway.