The planned activities for
the week of 4/22/02 are as follows:
- Continue storm drain installation along the south side of the Distribution
Center building, as well as other site drainage.
- Continue importing borrow.
- Excavation of borrow soil from the softball field area.
- Placement of topsoil layer for surface restoration.
- Continue subgrade and finish grading across site.
- Installation of monitoring well network is ongoing.
Activities conducted during
the week of 4/15/02 include:
- Continued to import borrow.
- Continued to work on dam: Placed concrete fill underpinning granite
blocks around culvert pipe and for under granite cheek stones.
- Continued to install site drainage.
- Continued to bring grades up to Phase I sub-grade on top of engineered
barrier in and around recreation and soccer fields.
- Continued to place material along the west side of the consolidation
area adjacent to planned track.
- Continued to fine grade slopes along wetlands and water quality swale
and place top soil.
- Continued to lower the grade of the softball field to generate borrow.
- Decommissioned monitoring wells at MW-24 due to storm drain installation
in close proximity