What's New

Paint Shop Pond

History and Location

Pre-Cleanup Investigations

Cleanup Plan

Fact Sheets

Glossary, Q+A

Contacts

 

The planned activities for the week of 4/8/02 are as follows:

  1. Continue installing peat in the wetland area along the edge of Paintshop Pond.
  2. Continue storm drain installation along the south side of the Distribution Center building.
  3. Continue granite work around Paintshop Pond dam.
  4. Place channel stone subgrade.
  5. Installation of supplemental warning layer (snow fence) over portion of the engineered barrier.
  6. Touch-up grading of the Waban Brook channel and adjacent peat in the southern wetland.
  7. Continue subgrade and finish grading across site.
  8. Excavation of borrow soil from the softball field area.
  9. Upgrade truck access roadways on site for Phase I and II deliveries.
  10. Installation of monitoring well network is ongoing

    Activities conducted during the week of 4/1/02 include:
  1. Continued installing peat in the wetland area along the edge of Paintshop Pond.
  2. Continued storm drain installation along the south side of the Distribution Center building.
  3. Completed installation of select borrow over the engineered barrier as well as installation of cap drainage system.
  4. Continued granite work around Paintshop Pond dam.
  5. Touch-up grading of the Waban Brook channel.
  6. Continued subgrade and finish grading across site.

Click here for the list of archived What's New files.


Maintained by the Office for Public Information
Last Modified: April 25, 2002
paintshop pond