The planned activities for
the week of 4/8/02 are as follows:
- Continue installing peat in the wetland area along the edge of Paintshop
Pond.
- Continue storm drain installation along the south side of the Distribution
Center building.
- Continue granite work around Paintshop Pond dam.
- Place channel stone subgrade.
- Installation of supplemental warning layer (snow fence) over portion
of the engineered barrier.
- Touch-up grading of the Waban Brook channel and adjacent peat in
the southern wetland.
- Continue subgrade and finish grading across site.
- Excavation of borrow soil from the softball field area.
- Upgrade truck access roadways on site for Phase I and II deliveries.
- Installation of monitoring well network is ongoing
Activities conducted during
the week of 4/1/02 include:
- Continued installing peat in the wetland area along the edge of Paintshop
Pond.
- Continued storm drain installation along the south side of the Distribution
Center building.
- Completed installation of select borrow over the engineered barrier
as well as installation of cap drainage system.
- Continued granite work around Paintshop Pond dam.
- Touch-up grading of the Waban Brook channel.
- Continued subgrade and finish grading across site.