|
The planned activities for
the week of 8/13/2001 are as follows:
- Continue contaminated stump grinding.
- Installation of emergency overflow diversion tube.
- Installation of sump(s) in Paintshop Pond for dewatering.
- Continue bulk excavation of clean borrow soils from Borrow Area A,
creating additional consolidation area footprint.
- Continue excavating clean and contaminated peat materials from the
Northern Wetland, with subsequent backfill with clean materials.
- Continued dewatering in Northern Wetland using miscellaneous sumps.
- Complete the main dewatering sump velocity dispersion measures and
header piping.
- Limited tree clearing in the Distribution Center upper parking lot
area.
Activities conducted during
the week of 8/6/2001 include:
- Excavated contaminated and clean peat from the Northern Wetlands and
contaminated soils from upland areas.
- Continued backfilling Northern Wetland with clean borrow to create
clean pad.
- Completed excavation of contaminated soils on top of the former tennis
courts and relocated the materials to the treatment area.
- Excavated clean borrow soils for backfill in Northern Wetlands and
upland areas.
- Continue improvements to the multi-media filter, including installation
of main dewatering sump velocity dispersion system.
- Chipping contaminated stumps.
- Construction of a wet peat drying area in the contaminated uplands.
- Continued dust control and surface water diversion.
Click here for the list of archived What's
New files.
Maintained by the Office
for Public Information
Last Modified: August 14, 2001
paintshop pond
|