The planned
activities for the week of 8/27/2001 are as follows:
- Begin mobilizing equipment and materials for in-situ
soil treatment.
- Complete upper Distirbution Center parking lot
remediation. Restoration work will continue through
week.
- Tree clearing along Route 135 for soil treatment
staging area..
- Begin removing contaminated sediments from south end
of Paintshop Pond.
- Begin installing sheetpile in front of Paintshop Pond
Dam.
- Completion of diversion tube.
- Continue grinding and chipping of contaminated
stumps.
- Continue Northern Wetland excavation and
backfilling.
Activities
conducted during the week of 8/20/2001 include:
- Began Upper Distribution Center parking lot
remediation.
- Continued contaminated and clean peat removal from
the Northern Wetlands, with subsequent backfill.
- Continued stockpiling clean peat in Borrow Area B
gravel pit (ongoing).
- Began Paintshop Pond sediment removal, including
installation of miscellaneous sumps..
- Completed overflow diversion tube construction.
- Continued consolidation area construction.
- Ongoing main dewatering sump improvements, including
installation of bag filters..