The planned activities for
the week of 8/6/2001 are as follows:
- Excavate contaminated and clean peat out of the Northern Wetlands.
- Excavate contaminated uplands.
- Construction of an intermediate dewatering area for excessively wet
contaminated northern wetland material within the uplands.
- Stockpile clean peat removed from the Northern Wetland in the gravel
pit.
- Continue excavation, placement and compaction of clean borrow materials
around site.
- Relocate the pigment-contaminated soils from atop the former tennis
courts to the treatment area adjacent to Paintshop Pond.
- Continue upgrading main dewatering sump water discharge control measures
in Lake Waban.
- Continue chipping contaminated stumps.
Activities conducted during
the week of 7/30/2001 include:
- Continued excavating contaminated peat from Northern Wetland and stockpiling
in consolidation area.
- Continuee backfilling Northern Wetland with clean borrow to create
clean pad.
- Began excavating clean peat from Northern Wetland and stockpiling
in gravel pit area.
- Excavated contaminated uplands immediately west of Northern Wetland.
- Completed construction of main dewatering sump.
- Installed multi-media filter at main dewatering sump.
- Continuee removing stumps in contaminated area.