|
The planned activities for
the week of 12/10/2001 are as follows:
- Remedial excavation in remaining southern wetland area adjacent to
main dewatering sump.
- Ongoing Paintshop Pond dam and wall restoration. Stone mason may begin
mobilization. Install subgrade soils between the retaining walls and
pour concrete pier footing for precast arch bridge sections.
- Proposed southern wetland subgrade preparation and peat installation.
- May shut down main dewatering sump and remove equipment. Continue
dewatering from temporary dewatering sump.
- Placement of fill for the water quality swale located on the south
side of the consolidation area berm.
- Continue managing soil in the consolidation area.
- May manufacture additional sand borrow.
- Placement and compaction of semi-pervious fill adjacent to Paintshop
Pond dam
- Miscellaneous excavation of borrow soil and peat and filling.
- Installation of woven geotextile fabric layer (recent addition to
engineered barrier configuration) and six-inch sand borrow layer on
eastern field to prepare for HDPE liner installation (east field only).
Anticipate beginning HDPE placement on the eastern portion of the consolidation
area on 12/17/01.
- Continue re-dredging cells that were recontaminated by the trailing
curtain.
- Collect additional post-dredge verification samples in areas previously
dredged.
- Load out treated and tested soil.
- Treat soil/pigment (using ferrous sulfate as an amendment to the calcium
polysulfide reagent).
- Continue health and safety air monitoring.
Activities conducted during
the week of 12/3/01 include:
- Ongoing Paintshop Pond dam and wall restoration.
- Miscellaneous excavation of borrow soil and filling.
- Southern wetland subgrade preparation and peat installation.
- Began shutting down main dewatering sump (i.e., removed some of equipment).
Continue dewatering from temporary dewatering sump.
- Excavate and relocate to consolidation area pigment-contaminated soil
in the vicinity of G3 discovered while excavating borrow.
- Continued management of soil in the consolidation area.
- Restoration of field hockey field remediation area.
- Begin placement and compaction of semi-pervious fill to south of Waban
Brook.
- Continue hauling partially-dewatered northern shoreline dredge material
to the consolidation area
- Took delivery of 26 rolls of 60-mil HDPE geomembrane.
- Reposition/create new site access ramp, including relocation of a
construction and two equipment trailers.
- Treat soil and pigment (using ferrous sulfate as an amendment to the
calcium polysulfide reagent).
- Load out treated and tested soil.
- Continued re-dredging area NS-2.
- Dredged spoils were loaded into barges for primary de-watering. Maxymillian
Technology is using a barge equipped with a sump to de-water dredged
spoils prior to transport to the shoreline. Barges are then transported
to shore where material is excavated from barge loaded into trucks and
placed in the uplands.
- Continue health and safety air monitoring.
Click here for the list of
archived What's New files.
Maintained by the Office
for Public Information
Last Modified: December 11, 2001
paintshop pond
|