|
The planned activities for
the week of 12/24/2001 are as follows:
- Remedial excavation in remaining Southern Wetland area adjacent to
main dewatering sump.
- Stone mason to mobilize.
- Southern Wetland, wetland south of Paintshop Pond, and Waban Brook
subgrade preparation and peat installation.
- Continue dewatering from temporary dewatering sump.
- Continue with remedial excavation in the area to north of the IT treatment
area.
- Continue managing soil in the remaining consolidation area (west field
area).
- Manufacture additional sand borrow or select borrow.
- Placement and compaction of semi-pervious fill adjacent to Paintshop
Pond dam (weather permitting).
- Miscellaneous excavation of borrow soil and filling.
- Miscellaneous excavation of contaminated soil (if encountered).
- Excavate for bridge abutement (bridge over Waban Brook connected to
the boardwalk).
- Begin installing screw piles for boardwalk through wetland.
- Install geocomposite drain over the east field.
- Ongoing management of partially-dewatered sediment from northern shoreline/western
cove dredging in consolidation area.
- Complete final remediation around PSP dam area.
- Continue to treat soil/pigment (using ferrous sulfate and/or calcium
polysulfide reagent).
- Mix in dry materials to reduce moisture content of treated material
before excavating and relocating to consolidation area.
- Dredge cell V3 in accordance with Dept. of Environmental Protection
(DEP) request.
- Begin placing sand and gravel cap near mouth of Upper Waban Brook,
if approved by DEP.
- Continue health and safety air monitoring.
Activities conducted during
the week of 12/17/01 include:
- Remedial excavation in remaining southern wetland area adjacent to
main dewatering sump.
- Ongoing Paintshop Pond dam and wall restoration. Installed double
arch bridge sections.
- Waban Brook subgrade preparation and channel construction.
- Continue dewatering from temporary dewatering sump.
- Placement of fill and grading for the water quality swale located
on the south side of the consolidation area berm.
- Continued management of soil in the consolidation area.
- Continued manufacture additional sand borrow.
- Ongoing management of partially-dewatered sediment from northern shoreline/western
cove dredging in consolidation area.
- Miscellaneous excavation of borrow soil and peat and filling.
- Resizing and off-site transport of felled trees/logs.
- Continue subgrade grading on small portion of east field area to receive
woven geotextile and sand borrow.
- Continue Installation of woven geotextile fabric layer and 6-in. sand
borrow layer on eastern field to prepare for HDPE liner installation
(east field only).
- Install HDPE geomembrane over the east field (nearly complete).
- Removed temporary sheetpile cofferdam installed in front of PSP dam
and installed water control berm to allow equipment access.
- Removed main dewatering sump equipment.
- Continued to treat soil and pigment (using ferrous sulfate and/or
calcium polysulfide reagent).
- Mixed dry materials to reduce moisture content of treated material
before excavating and relocating to consolidation area.
- Load out treated and tested soil.
- Completed re-dredging area NS-1.
- Mobilized to grid cell V3. Dredged spoils were loaded into barges
for primary de-watering. Maxymillian Technology is using a barge equipped
with a sump to de-water dredged spoils prior to transport to the shoreline.
Barges are then transported to shore where material is excavated from
barge loaded into trucks and placed in the uplands.
- Continue health and safety air monitoring.
Click here for the list of
archived What's New files.
Maintained by the Office
for Public Information
Last Modified: January 10, 2002
paintshop pond
|