|
The planned activities for
the week of 12/3/2001 are as follows:
- Remedial excavation in remaining southern wetland area adjacent to
main dewatering sump.
- Ongoing Paintshop Pond dam and wall restoration. Stone mason may begin
mobilization.
- Proposed southern wetland subgrade preparation and peat installation.
- Shut down main dewatering sump and remove equipment. Continue dewatering
from interim temporary dewatering sump (see below).
- Reduce size of clean concrete chunks (possible).
- Continue managing soil in the consolidation area.
- Restoration of field hockey field remediation area.
- Begin placement and compaction of semi-pervious fill to south of Waban
Brook.
- Continue re-dredging cells that were recontaminated by the trailing
curtain.
- Collect additional post-dredge verification samples in areas previously
dredged.
- Miscellaneous excavation of borrow soil and filling.
- Treat soil/pigment (using ferrous sulfate as an amendment to the calcium
polysulfide reagent).
- Continue health and safety air monitoring.
Activities conducted during
the weeks of 11/19 and 11/26/2001 include:
- Continued the ongoing Paintshop Pond dam and wall restoration (including
installation of steel reinforcement, concrete forms, etc. for footings
and wall sections).
- Completed remediation at the southern end of the south wetland.
- Extended section of proposed Waban Brook.
- Installed interim temporary dewatering sump at the end of the section
of restored Waban Brook. Continued operation of main dewatering sump.
- Prepared proposed southern wetland subgrade and installed peat for
portion of proposed wetland area.
- Completed remedial excavation in the field hockey field area, including
beginning the restoration.
- Continue operation of the soil screen plant, creating topsoil borrow
and sand borrow.
- Excavation of borrow soil from Borrow Area B and filling.
- Conducted remedial excavation in the area to the north of IT treatment
area. Some additional remedial excavation in area to north of IT treatment
area remains to be conducted.
- Continued management of material within the consolidation area.
- Remediated portions of southern wetland and Waban Brook.
- Created new haul road into consolidation area for dredge material
from Lake Waban.
- Completed dredging cells F4, G4, and WC1 in northern shoreline/western
cove area.
- Began re-dredging cells E3 & E4 and portions of area NS-2.
- Continued to collect additional post-dredge verification samples in
areas previously dredged, and confirmatory samples at grid cells that
did not require dredging to confirm that contaminants have not migrated
to these areas during dredging.
- Dredged spoils were loaded into barges for primary de-watering. Maxymillian
Technology is using a barge equipped with a sump to de-water dredged
spoils prior to transport to the shoreline. Barges are then transported
to shore where material is excavated from barge loaded into trucks and
placed in the Uplands.
- Relocation of several loads of lime green pigment encountered during
excavation to IT for treatment.
- Treated soil and pigment.
- Took delivery and used ferrous sulfate as an amendment to the calcium
polysulfide reagent.
- Relocated material storage area and construction trailers to area
south of treatment area.
- Continue health and safety air monitoring.
Click here for the list of
archived What's New files.
Maintained by the Office
for Public Information
Last Modified: December 4, 2001
paintshop pond
|