The planned activities for the week of 12/31/2001 are as follows:

 

  1. Remedial excavation in remaining southern wetland area adjacent to main dewatering sump (remediation work is nearly complete).
  2. Stone mason to mobilize.
  3. Southern wetland, wetland south of Paintshop Pond, and Waban Brook subgrade preparation and peat installation.
  4. Continue dewatering from temporary dewatering sump.
  5. Continue with remedial excavation in the area adjacent to G3 at the southeast corner of the IT treatment area.
  6. Continue managing soil in the remaining consolidation area (west field area).
  7. Manufacture additional sand borrow or select borrow.
  8. Placement and compaction of semi-pervious fill adjacent to Paintshop Pond dam (weather permitting).
  9. Miscellaneous excavation of borrow soil and filling.
  10. Miscellaneous excavation of contaminated soil (if encountered).
  11. Backfilling in Lake Waban for capping.
  12. Begin installing screw piles for boardwalk through wetland.
  13. Install geocomposite drain over the east field.
  14. Pour bridge abutment for bridge over Waban Brook.
  15. Continue installing drainage blanket, stone, and filter fabric on exterior of retaining walls downstream of dam.
  16. Continue to treat soil/pigment (using ferrous sulfate and/or calcium polysulfide reagent).
  17. Mix in dry materials to reduce moisture content of treated material before excavating and relocating to consolidation area.
  18. Continue placing sand and gravel cap near mouth of Upper Waban Brook
  19. Continue health and safety air monitoring.

    Activities conducted during the week of 12/24/01 include:
  1. Remedial excavation in remaining southern wetland area adjacent to main dewatering sump.
  2. Ongoing Paintshop Pond dam and wall restoration. Installed double arch bridge sections.
  3. Waban Brook subgrade preparation and channel construction.
  4. Continue dewatering from temporary dewatering sump.
  5. Placement of fill and grading for the water quality swale located on the south side of the consolidation area berm.
  6. Continued management of soil in the consolidation area.
  7. Continued manufacture additional sand borrow.
  8. Ongoing management of partially-dewatered sediment from northern shoreline/western cove dredging in consolidation area.
  9. Miscellaneous excavation of borrow soil and peat and filling.
  10. Resizing and off-site transport of felled trees/logs.
  11. Continue subgrade grading on small portion of east field area to receive woven geotextile and sand borrow.
  12. Continue Installation of woven geotextile fabric layer and 6-in. sand borrow layer on eastern field to prepare for HDPE liner installation (east field only).
  13. Install HDPE geomembrane over the east field (nearly complete).
  14. Removed temporary sheetpile cofferdam installed in front of PSP dam and installed water control berm to allow equipment access.
  15. Removed main dewatering sump equipment.
  16. Continued to treat soil and pigment (using ferrous sulfate and/or calcium polysulfide reagent).
  17. Mixed dry materials to reduce moisture content of treated material before excavating and relocating to consolidation area.
  18. Load out treated and tested soil.
  19. Completed dredging grid cell V3
  20. Mobilized to mouth of Upper Waban Brook for placement of sand and gravel cap and began placing sand & gravel cap as approved by DEP.
  21. Haley & Aldrich collected additional samples from cells F2, G3, and H3. XRF results showed sediment concentrations in these cells to be above the remedial goal for lead.
  22. Continue health and safety air monitoring.