What's New

Paint Shop Pond

History and Location

Pre-Cleanup Investigations

Cleanup Plan

Fact Sheets

Glossary, Q+A

Contacts

 

The planned activities for the week of 2/25/2002 are as follows:

 

  1. Continue boardwalk and bridge carpentry.
  2. Begin surcharge loading in west field of consolidation area.
  3. Continue managing soil and grading in the remaining consolidation area (west field area).
  4. Continue restoration work, shaping slopes around the site.
  5. Continue preparing subgrades across site.
  6. Repair crack in top of poured concrete cap on PSP dam.
  7. Placement and compaction of imported fill.
  8. Stone mason completed setting stone; may set cut granite blocks in channel if they arrive.
  9. Set and pour detention basin outlet structure for the detention basin.
  10. Storm drain installation.
  11. Continue to treat soil/pigment (using ferrous sulfate and/or calcium polysulfide reagent).
  12. Begin consolidating treatment work area.
  13. Begin consolidating the work area and doing final cleanup of haul roads and work areas.
  14. Begin decontaminating and demobilizing equipment.
  15. Continue health and safety air monitoring.

    Activities conducted during the week of 2/18/02 include:
  1. Continued placement and compaction of imported fill.
  2. Continue managing soil in the remaining consolidation area (west field area).
  3. Continued restoration work, shaping slopes along the edge site.
  4. Continue preparing subgrades across site.
  5. Completed manufacture of topsoil.
  6. Continued boardwalk and bridge carpentry.
  7. Took hydraulic oil contaminated soil off site for disposal.
  8. Took transite pipe off site for disposal.
  9. Began cutting in paths outside the fenced worked area.
  10. Performed miscellaneous excavation of contaminated soil and relocation to the consolidation area.
  11. Demobilized some equipment, including excavator in treatment area.
  12. Treated soil/pigment (using ferrous sulfate and/or calcium polysulfide reagent).
  13. Excavated treated and tested soil.
  14. Consolidated treatment work area.
  15. Continue health and safety air monitoring.

Click here for the list of archived What's New files.


Maintained by the Office for Public Information
Last Modified: March 4, 2002
paintshop pond