|
The planned activities for
the week of 1/7/2002 are as follows:
- Stone mason to begin setting stone.
- Southern wetland, wetland south of Paintshop Pond, and Waban Brook
subgrade preparation and peat installation.
- Begin screw pile installation for boardwalk
- Dewatering from temporary dewatering sump (occasional dewatering as
needed).
- Continue with remedial excavation in the area adjacent to G3 at the
southeast corner of the IT treatment area.
- Continue managing soil in the remaining consolidation area (west field
area).
- Manufacture additional select borrow.
- Placement and compaction of semi-pervious fill adjacent to Paintshop
Pond dam (weather permitting)
- Miscellaneous excavation of borrow soil and filling.
- Miscellaneous excavation of contaminated soil (if encountered).
- Backfilling in Lake Waban for capping.
- Begin placing select borrow over the geocomposite and geomembrane.
- Excavation of hydraulic fill in uplands east of IT treatment area
and onsite reuse as semi-pervious fill adjacent to the PSP dam area.
- Continue to treat soil/pigment (using ferrous sulfate and/or calcium
polysulfide reagent).
- Mix in dry materials (if necessary) to reduce moisture content of
treated material before excavating and relocating to consolidation area.
- Continue health and safety air monitoring.
Activities conducted during
the week of 12/31/01 include:
- Remedial excavation in remaining southern wetland area adjacent to
main dewatering sump (remediation work is complete in southern wetland).
- Stone mason mobilized.
- Southern wetland, wetland south of Paintshop Pond, and Waban Brook
subgrade preparation and peat installation.
- Continue dewatering from temporary dewatering sump until Friday 1/4/02
(taken offline except for emergency use).
- Continue installing drainage blanket, stone, and filter fabric on
exterior of retaining walls downstream of dam.
- Continued management of soil in the remaining consolidation area (west
field area).
- Continued to manufacture additional sand borrow.
- Placement and compaction of semi-pervious fill adjacent to Paintshop
Pond dam.
- Miscellaneous excavation of borrow soil and peat and filling.
- Miscellaneous excavation of contaminated soil.
- Backfilling in Lake Waban for capping.
- Completed HDPE installation and QAQC, as well as install geocomposite
drain over the east field.
- Installed steel reinforcement and poured concrete bridge abutment
for bridge over Waban Brook.
- Continued to treat soil and pigment (using ferrous sulfate and/or
calcium polysulfide reagent).
- Mixed dry materials to reduce moisture content of treated material
before excavating and relocating to consolidation area.
- Load out treated and tested soil.
- Mobilized to mouth of Upper Waban Brook for placement of sand and
gravel cap and began placing sand & gravel cap as approved by DEP.
- Haley & Aldrich collected additional samples from cells F2, G3, and
H3. XRF results showed sediment concentrations in these cells to be
above the remedial goal for lead.
- Continue health and safety air monitoring.
Click here for the list of
archived What's New files.
Maintained by the Office
for Public Information
Last Modified: January 10, 2002
paintshop pond
|