|
The planned
activities for the week 7/1/2001 are as follows:
- Put fininshing touches including drainage stone on the slope in the
northeast corner of the consolidation area under construction. The northeast
corner should be completed by the end of the week.
- Continue dust control.
- Install sumps and plumbing for the water diversion system at the Paintshop
Pond cofferdam.
- Load and transport wood chips off site.
- Begin to lower Paintshop Pond.
- Continue clearing in contaminated zones.
- Continue driving sheetpile cofferdam in Lake Waban.
- Setting two 24-in. HDPE pipes into velocity dissipator.
- Electrical connection for Paintshop Pond pump station by Town.
Work activities
completed during the week of 6/25/2001 include:
- Installed electrical conduit for Paintshop Pond diversion pumps along
Rt. 135.
- Clearing in the vicinity of the former paint factory south of Upper
Waban Brook.
- Continued constructing northeast corner of consolidation area. Majority
of cut excavation completed in the northeast corner portion.
- Continuing Lake Waban cofferdam installation (nearly 3/4 complete
with sheetpile installation).
- Continued removing wood chips from site.
- Completed 24-in. HDPE pipe welding and aligned along the western shoreline
of Paintshop Pond.
- Installed 5-ft diameter culvert in Upper Waban Brook to create an
additional access road to areas south of Waban Brook.
Click here for the list of archived
What's New files.
Maintained by the Office for Public Information
Date Created: July 17, 2001
Last Modified: July 17, 2001
paintshop pond
|