The planned
activities for the week 7/8/2001 are as follows:
- Finish installing pumps and plumbing in pump station at Paintshop
Pond cofferdam. Electrical connections planned for Wednesday.
- Finish loading wood chips for off site transport.
- Cutting/chipping trees/vegetation stockpiled on site.
- Draining Paintshop Pond.
- Removing/relocating fish from Paintshop Pond.
- Trench along the north slope of the consolidation area and place stone
in trench and along slope.
- Installing temporary storm drain extension pipe for existing storm
drain discharge in northeast corner of the consolidation area.
- Begin stump removal in Northern Wetland.
- Complete Lake Waban cofferdam.
- Constructing main dewatering sump.
- Athletic department storage shed demolition and disposal.
- Continue dust control
Work activities
completed during the week of 7/1/2001 include:
- Load and transport wood chips off site.
- Begin to lower Paintshop Pond.
- Continue clearing in contaminated zones.
- Continue driving sheetpile cofferdam in Lake Waban.
- Continued constructing northeast corner of consolidation area. Majority
of cut excavation completed in the northeast corner portion.
- Continuing with ductile iron plumbing for surface water diversion.
- Excavated Waban Brook bypass channel through contaminated uplands
south of Waban Brook and north of the walking path.
- Expanded access road around the Northern Wetland to provide access
and work space for long-reach excavator to be used in Northern Wetland
remediation.