|
The planned activities for
the week of 6/10/02 are as follows:
- Install armor stone in Waban Brook (pending stone delivery). Begin
armoring channel adjacent to the granite stones (pending stone delivery).
- Continue removal of surface water bypass piping.
- Continue erosion control in wetlands, placing leaf mulch, and planting
wetlands.
- Continue topsoil touch-up and seed.
- Begin water intake structure and pump station.
- Decommission/fill velocity dissipater.
- Continue storm drain work around site.
Activities conducted from
5/20/02 - 6/7/02 include:
- Continued installing Waban Brook erosion controls (including slight
deepening of brook and armoring at outside of bends).
- Recompacted the last lift in the track and field area to 95 percent.
- Continue erosion control in wetlands, placing leaf mulch, and started
planting in wetlands.
- Continued placement of topsoil (with annual seed mix) and minor subgrade
fine placement, grading, and compaction.
- Completed stone masonry around Paintshop Pond dam.
- Began and continued removal of Paintshop Pond diversion pump station,
sheeting and piping.
- Continue placement of topsoil and seed.
- Mobilization and site preparation for water intake structure and pump
station.
Click here for the list of archived What's
New files.
Maintained by the Office
for Public Information
Last Modified: July 17, 2002
paintshop pond
|