The planned activities for the week of 6/24/02 are as follows:

  1. Continue storm drain work around site.
  2. Continue erosion control in wetlands, placing leaf mulch, and planting wetlands.
  3. Continue water intake structure and pump station.
  4. Armoring in Waban Brook.

    Activities conducted from 6/10/02 - 6/21/02 include:
  1. Continued removal of surface water bypass piping.
  2. Continued storm drain work around site.
  3. Continued erosion control in wetlands, placing leaf mulch, and planting wetlands.
  4. Continued topsoil touch-up and seed.
  5. Began water intake structure and pump station.
  6. Decommission/fill velocity dissipater.