The planned activities for
the week of 3/11/02 are as follows:
- Install woven geotextile and sand borrow over the west field of the
consolidation area.
- Install HDPE liner and geocomposite (scheduled for 3/12/02).
- Storm drain installation.
- Continue restoration work, including wetland restoration along the
edge of PSP.
- Continue preparing subgrades across site.
- Erosion control maintenance.
- Placement and compaction of imported fill.
- May receive cut granite blocks.
- Continue health and safety air monitoring.
Activities conducted during
the week of 3/4/02 include:
- Completed boardwalk and bridge carpentry.
- Completed surcharge loading in west field of consolidation area.
- Continue managing soil and grading in the remaining consolidation
area (west field area).
- Continued restoration work, including preparing subgrades across site.
- Shut off surface water diversion pumps.
- Placement and compaction of imported fill.
- Storm drain installation.
- Scraped down last of the haul road material and placed in the consolidation
area.
- Installed woven geotextile and sand borrow over the west field of
the consolidation area to prepare for HDPE liner installation (tentatively
scheduled for 3/11/02).
- Removed drums of oil-contaminated soil from small spill (non-reportable)
and cleanup.
- Continued health and safety air monitoring.