|
The planned activities for
the week of 3/18/02 are as follows:
- May receive cut granite blocks.
- Begin installing 18-in. layer of select borrow over the top of the
geosynthetics of the engineered barrier.
- Begin installing perimeter and interior drain for the engineered barrier.
- Continue restoration work, including wetland restoration along the
edge of PSP.
- Continue preparing subgrades across site; including wetlands subgrade
and lowering of the softball field to generate additional borrow soils
to use around the site.
- Select equipment demobilization.
- Installation of the slide gate for the PSP dam.
Activities conducted during
the week of 3/11/02 include:
- Completed installing woven geotextile and sand borrow over the west
field of the consolidation area.
- Completed HDPE liner and geocomposite installation.
- Continued restoration work, including wetland restoration along the
edge of PSP.
- Placement/stockpiling of imported fill.
- Continued preparing subgrades across site, including lowering the
softball field to generate borrow soils for use around the site.
- Discontinued perimeter air monitoring.
Click here for the list of
archived What's New files.
Maintained by the Office
for Public Information
Last Modified: March 26, 2002
paintshop pond
|