The planned activities for
the week of 3/25/02 are as follows:
- Receive additional cut granite blocks and begin installation.
- Receive and possibly install slide gate bearing and controller.
- Likely finish grading of peat along the wetland replacement area
along the edge of Paintshop Pond.
- Slight reshaping of Waban Brook and touch-up work on the peat grading
in the southern wetland.
- Continue equipment demobilization.
- Steel fabrication on Paintshop Pond dam.
- Continue storm drain installation.
- Complete installing 18-in. layer of select borrow over the top of
the geosynthetics of the engineered barrier.
- Complete installing perimeter and interior drain for the engineered
barrier.
- Continue subgrade preparation work across site.
- Operate surface water diversion pumps as needed.
Activities conducted during
the week of 3/18/02 include:
- Received portion of cut granite blocks for PSP dam restoration.
- Installed portion of 18-in. layer of select borrow over the top of
the geosynthetics of the engineered barrier.
- Installed portion of perimeter and interior drain for the engineered
barrier.
- Continue restoration work, including wetland restoration along the
edge of Paintshop Pond.
- Continue preparing subgrades across site including wetlands subgrade
and lowering of the softball field to generate additional borrow soils
to use around the site.
- Storm drain installation and detention basin work.
- Installation of the slide gate for the Paintshop Pond dam.