The planned activities for
the week of 5/13/02 are as follows:
- Continue preparing Waban Brook erosion controls (bio logs due early
in week).
- Begin removal of Paintshop Pond diversion pump station (pending weather/flow
conditions).
- Continue erosion control in wetlands, placing leaf mulch, and possibly
start to plant wetlands.
- Continue site grading and placement of topsoil.
- Begin installing indicator strip around the engineered barrier.
- Installation of monitoring well network is ongoing.
Activities conducted during
the week of 5/6/02 include:
- Completed Phase I storm drain work.
- Continued subgrade and finish grading across site.
- Completed borrow soil excavation. Completed borrow import.
- Placement of topsoil layer for surface restoration.
- Granite work around PSP dam: including cheek stones and remainder
of cap stones.
- Wetlands restoration subcontractor began installation of erosion controls.
- Steel work associated with the PSP Dam slide gate.