The planned activities for
the week of 4/29/02 are as follows:
- Continue storm drain work.
- Continue subgrade and finish grading across site.
- Nearly complete with borrow soil excavation; completed borrow import.
- Placement of topsoil layer for surface restoration.
- Granite work around PSP dam: including cheek stones and remainder
of cap stones.
- Begin installing railings along retaining walls.
- Wetlands restoration subcontractor begins installation of erosion
controls and leaf mulch.
- Steel work associated with the PSP dam slide gate.
- Installation of monitoring well network is ongoing.
Activities conducted during
the week of 4/29/02 include:
- Continued storm drain work including frames and covers.
- Continued and finished with importing borrow.
- Excavation of borrow soil from the softball field area.
- Placement of topsoil layer for surface restoration.
- Continued subgrade and finish grading across site.
- Spreading grass seed.