The planned activities for the week of 4/29/02 are as follows:

  1. Continue storm drain work.
  2. Continue subgrade and finish grading across site.
  3. Nearly complete with borrow soil excavation; completed borrow import.
  4. Placement of topsoil layer for surface restoration.
  5. Granite work around PSP dam: including cheek stones and remainder of cap stones.
  6. Begin installing railings along retaining walls.
  7. Wetlands restoration subcontractor begins installation of erosion controls and leaf mulch.
  8. Steel work associated with the PSP dam slide gate.
  9. Installation of monitoring well network is ongoing.

    Activities conducted during the week of 4/29/02 include:
  1. Continued storm drain work including frames and covers.
  2. Continued and finished with importing borrow.
  3. Excavation of borrow soil from the softball field area.
  4. Placement of topsoil layer for surface restoration.
  5. Continued subgrade and finish grading across site.
  6. Spreading grass seed.