The planned activities for
the week of 10/1/2001 are as follows:
- Continue dredging in Lake Waban and managing material in uplands decant
area.
- Continue uplands remedial excavation adjacent to the southern wetlands.
- Uplands remedial excavation adjacent to and downstream of the Paintshop
Pond dam for purposes of installing concrete footings and wingwalls..
- Excavation of clean Borrow B material for miscellaneous filling operations.
- Continue removing contaminated Southern Wetland peat.
- Continue spreading contaminated material in the consoldation area
along the bottom of the completed clean pad of the consolidation area.
- Finish restoration of upper Distribution Center parking lot.
- Continue operation of multi-media and bag filter treatment system
at the main dewatering sump.
- Construct mock-up of the retaining wall with stone facade.
- Conduct health and safety air monitoring.
- Install slope stabilization berm along outside (eastern edge) of Northern
Shoreline/Western Cove area "NS-2".
Activities conducted during
the week of 9/24/2001 include:
- Nearly completed consolidation area south berm.
- Uplands remedial excavation adjacent to and downstream of the Paintshop
Pond dam for purposes of installing concrete footings and wingwalls.
- Excavation of clean Borrow B material for miscellaneous filling operations.
- Continued removing contaminated Southern Wetland peat.
- Spread contaminated material in the consoldation area along the bottom
of the completed clean pad of the consolidation area.
- Continue bringing contaminated Northern Wetland peat stockpiled in
Uplands for drying to the consolidation area.
- Continue operation of multi-media and bag filter treatment system
at the main dewatering sump.
- Completed Versalock retaining wall blocks in the upper Distribution
Center parking lot.
- Construct mock-up of the retaining wall with stone facade.
- Started uplands remedial excavation in the vicinity of the former
settling lagoons.
- Relocated dredged Northern Shoreline sediments to decant stockpile
area.
- Poured concrete for right (south) wingwall.
- In Northern Shoreline/Western Cove, completed dredging area "NS-1",
located immediately south of the mouth of Upper Waban Brook.
- Began dredging the western portion of area "NS-2."